10 MW Wind Farm in Mavragani - Lykotopi

10 MW Wind Farm in Mavragani - Lykotopi, Southern Kynouria Municipality (Arcadia)
10 MW Wind Farm  in Mavragani - Lykotopi
2011
ENERGY DESIGN CO
Finished

Wind farm consisting of 5 wind turbines with a rated power of 2 MW each.

The objective of the study is to create a network of internal roads during the construction and operation phases of the project.

Wind farm infrastructure projects as follows:

a) New substation MV / HV.
b) Electric line consisting of underground cables will be at a voltage of 20,000 volts, total length about 6 km, for the transfer of energy from Wind Farm in the substation
c) Internal wind farm road construction

View also
ENCODIA serves both public and private sectors and up to this date, we offer solutions and support to a variety of engineering fields.
Environmental permit modification for Psilos Cavos fish farming
Environmental permit modification for Psilos Cavos fish farming

Environmental permit modification for Psilos Cavos fish farming installation in Plateia Island.

Environmental permit for existing concrete plant in Veligosti, Municipality of Megalopolis
Environmental permit for existing concrete plant in Veligosti, Municipality of Megalopolis

Environmental permit renewal for an existing concrete plant in Veligosti, Municipality of Megalopolis.

Technical environmental study for Naxos' airport expansion
Technical environmental study for Naxos' airport expansion

Technical environmental study for Naxos' airport expansion construction.